VARIATION PROCEDURE CHECKLIST

Below is a detailed checklist surrounding the procedure, under AS400, that should be followed when variations in construction contracts arise.

Template

PROPOSED VARIATION NOTICE

The Superintendent on behalf of the Principal issues the Contractor a written Notice of Proposed Variation

Contractor identifies whether the project can be effected

Contractor provides Superintendent will written quotation  

Principal decides not to proceed and directs Contractor to continue with original scope or Principal accepts the variation price estimate and directs Contractor to proceed

DIRECTION TO EXECUTE VARIATION

Superintendent issues the Contractor a written Direction Notice

Contractor identifies whether the project cannot be effected

Contractor either approves or rejects variation

Contractor begins work

PRICING

Superintendent prices variation 

Superintendent adds or deducts variation cost from original contract sum

Contractor claims progress payments in regular scehduled payemtns 

WHEN THE PROPOSED VARIATION CAUSES A DELAY

As soon as possible once the Contractor becomes aware of possible delay they must give written notice to the Superintendent

If the project will result in a delay within 28 days the Contractor must lodge a written Extension of Time (EOT) claim

Superintendent either approves or rejects EOT claim 